Search: -30, Construction Projects, 07/09/2015

3 results

Results

Bond Project Sacramento Charter

Sacramento High AC Paving at East Parking Lot

 

Start Date: May 10, 2015

Target Date: August 28, 2015

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMR
  • Contractor: XL Construction
  • Funding Source: Emergency Repair Program

Construction Description: Paving at East parking lot

Bond Project

Edward Kelly Preschool Fire Alarm Upgrade

 

Start Date: May 1, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Lori Rubenstein
  • Architect: HMC
  • Contractor: Studebaker Brown
  • Funding Source: Measure Q

Construction Description: Fire alarm upgrade

Bond Project Sacramento Charter

Sacramento High AC Paving at North Parking Lot

 

Start Date: May 10, 2015

Target Date: August 28, 2015

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMR
  • Contractor: XL Construction
  • Funding Source: Emergency Repair Program

Construction Description: Paving at North parking lot