Search: -05, 06/2015

Results 11 - 20 of 38

Results

Press release

Two Â鶹¹û¶³´«Ã½ students named Gates Millennium Scholars
Award covers college tuition, living expenses for four years

June 8, 2015 (Sacramento):  Two Â鶹¹û¶³´«Ã½ students have been named Gates Millennium Scholars, an award that covers the cost of attending college for high-performing, low-income students of color.

Luther Burbank High School salutatorian Sabreena Singh, 18, and John F. Kennedy High School senior Manuel Valencia, 18, are among 1,000 students nationwide in the program’s Class of 2015. The scholarship is funded by a $1.6 billion grant from the Bill and Melinda Gates Foundation.

Bond Project Sacramento Charter

Sacramento High Stage Drapes and Rigging

 

Start Date: May 25, 2015

Estimated Completion Date: August 28, 2015 

 

Project Info: 

  • Project Manager: Jeff Bozeman; (916) 264-4075 Ext: 3617
  • Contractor: Stagecraft Industries, Inc.
  • Source Funding: Deferred Maintenance Program

Construction Description: Replacing stage drapes and rigging in theater

Bond Project Sacramento Charter

Sacramento High Pool Repairs

In-Construction

 

Start Date: July 20, 2015

Target Date: November 2015

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMR
  • Contractor: XL Contractors
  • Funding Source: Emergency Repair Program

Construction Description: Pool repairs

Bond Project Parkway

Parkway MP Water Damage

Before

 

Start Date: July 16, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Jeff Bozeman; (916) 264-4075 Ext: 3617
  • Architect: HMC
  • Contractor: McCarthy Builders
  • Funding Source: Emergency Repair Program

Construction Description: Stage flooring

Bond Project Sacramento Charter

Sacramento High Concrete (North Quadrant)

 

Start Date: May 7, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMR
  • Contractor: XL Construction
  • Funding Source: Emergency Repair Program

Construction Description: Concrete work in North Quadrant

Bond Project Clayton B. Wire Campus

Clayton B. Wire Fire Alarm Replacement

 

Start Date: May 15, 2015

Estimated Completion Date: August 28, 2015

 

Project Info: 

  • Project Manager: Anthony Lea; (916) 264-4075 Ext: 3616
  • Architect: HMC
  • Contractor: Studebaker Brown
  • Funding Source: Emergency Repair Program

Construction Description: Replacing existing fire alarms